The medium-voltage switchgear must be documented with a CAE system according to IEC 60 617.
Circuit diagrams, terminal connection diagrams, schematic diagrams, front views, constructional data and a single-line diagram must be prepared.
Complete detail drawings must be submitted for inspection and approval before starting manufacture and construction. Switchgear manufacture may only be started on the basis of released diagrams.
The documentation must be submitted as A4 format printouts and as pdf-file. The final revision must be supplied additionally on data carriers in dxf / dwg format.
Operating instructions
Operating instructions about transport, installation, connection and commissioning, maintenance and disposal are part of the scope of supply of the switchgear.
Offer documentation
The following must be enclosed with the offer:
Order documentation
The following documents are part of the scope of supply:
Texts included in circuit diagrams, front views, etc. will be in English as standard. Texts in other languages as well as customer-specific headers are possible.